\uD83D\uDDD3 Date
...
Item | Notes |
---|---|
|
|
Key Discussions |
|
...
ID | Description | Owner | Creation Date | Due Date | Status | Notes | ||||||
1 | Engagement Plan/Strategy Produce an engagement strategy for the operators. This will include what we need to engage on, who we need to engage with and when. | Samuel Ramos | July 19, 2022 | TBC in following meeting | In progress. Samuel to send the requested information to Kerri/Bonnie via email. Next Steps: Kerri/Bonnie to review. | Provide a clear estimation on how much work this will require with the contractors. We will need support from SS / support from Finance / IM/IT Killian sent to reviewers on 19/07 | ||||||
2 | Kerri to review the MVP and provide sign-off by the end of the week (July 29) | Kerri Harrison | July 19, 2022 | July 29, 2022 | Jul 22 – Kerri Reviewed and sent back to CGI. Kerri to sign-off |
| ||||||
3 | Explore the batch upload use case | Killian Faussart | July 19, 2022 |
| In Progress. | 4 | Communication Strategy CGI to make it clear to the HAs the benefits that CHEFS offer. Take the RKL and show the issues that have been identified and what the CHEFS tool is going to do as far as improvements go. | Samuel Ramos | July 19, 2022 | TBC | In Progress. Samuel, Eddy & Linda are working on getting a resource for the OCM component of the project, which will include this deliverable. | |
54 | Schedule a weekly meeting with the project team, Kerri, Heather, Bonnie, Jay | Samuel/Linda | July 19, 2022 | July 22, 2022 | Completed |
| ||||||
65 | Cut-off/Roll-out Plan Ask the health authorities when exactly they can be expected to start inputting their quarterlies. |
| July 19, 2022 | October 2022 | Open | Kerri’s preference is for FY22/23. Ideally, it would be good to have the budget first inputted, and then input the quarterly submission. |
...