Both Teams - Sprint 8 Report
CHEFS = Common HostEd Form Service
Red Team Planning
Sprint Goal:
Improving application stability, testing, and performance
Supporting and improving partner experience
Improving inclusion and accessibility capabilities
Dates: 27 June 2024 - 10 July 2024
JIRA Board: Active Sprint
Capacity: Total Capacity: 210
Estimated Deliverables: Backlog
Blue Team Planning
Sprint Goal
Start getting feedback about map component
Deliver mapping component
Tenant strategy incremental steps
Progress queue
POC for digital cred login
Dates: 27 June 2024 - 10 July 2024
JIRA Board: Active Sprint
Capacity: Total Capacity: 262.5
Estimated Deliverables: Backlog